Generation and rural electrification

LEC business

 

 

Electricity Generation
Generation of  Electricity falls outside the scope of the LEC business. Hence most of electricity is obtained from Muela and the small amount that Muela cannot supply from Eskom.  We do have 4 small mini  hydro-power stations in the mountains at Semonkong, Tlokoeng, Tsoelike and Mants'onyane. The Tsoelike station is decommissioned. The Tlokoeng station is also to be decommissioned now that Mokhotlong is connected to the grid. The plan is privaitize the Semonkong station and then only Mants'onyane will remain with LEC.
Rural  Electrification

Rural  Electrification Developments

By 1981 the construction of small-scale hydro electric plants was being contemplated. These were aimed at supplying electricity to the rural and remote mountain areas of the country, and at reducing diesel generation costs.

This plan was realized in 1988 when a 180kW mini hydro-plant in Semonkong was commissioned.The plant is situated along the Maletsunyane River in the Maseru district, and supplies about 26 consumers in the Semonkong development area.

In 1989 a 2 MW mini hydro plant situated along the Mantsonyane river was inaugurated. This mini hydro plant in the Thaba-Tseka region is connected to the National grid and supplies areas such as Roma, Molimo-Nthuse and Thaba-Tseka at times when the main grid is inoperative. During normal operation it is utilized for peak lopping, thus reducing the cost of electricity to LEC.

In 1990 two more mini hydro plants were commissioned: the Tlokoeng 670 kW plant situated along the Khubelu river (Mokhotlong) and the Tsoelike 400kW plant located along the Tsoelike river in Qacha?s Nek. Although the hydro plants were originally planned to serve the people living in the rural areas of Lesotho, they have generally been operating at a very limited scope. The main reason for this is the recurring drought the country has been experiencing. The acute water shortage has forced the implementation and use of costly diesel generators.

This has initiated plans to connect all these areas to the main electricity grids, in order to reduce the current high costs. Beneficiaries of these hydro plants are mainly hospitals, clinics, missions, commercial enterprises and a few domestic house holds.

Major Network Strengthening

In 1984 the company embarked on a long-term plan of improving the network system and furthering the extension of power to the rural areas. The 11kV circuits which connected Lesotho to Eskom were upgraded to 88kV / 33kV which was phased out in 1991 when the 132kV system was introduced. As of the introduction of 132 kV system in Lesotho, the 132 kV now extends to the South with the Ramarothole 132/33 kV substation, just outside the Mafeteng town. Further South, the 132 kV system extends to Mohale’s Hoek with the 132/33 kV substation at Litsoeneng in 2006. Whilst this has facilitated the availability of reliable supplies to industrial development in the South, the network extensions to the rural areas of Tŝakholo with the 11 kV network;  Ha Makhakhe and Thabana Morena with 33 kV network, have made it possible to extend to the rural areas.

In 1985 three more 33/11 kV substations were constructed at Mazenod, Roma and St. Agnes (Teyateyaneng). The Mazenod substation supplies the new Moshoeshoe I International airport with power.

In 1986 construction of four 33/11 kV substations at Highway, Botsabelo, Pioneer Road and Mohale’s Hoek started.

The additional 33/11 substations that have since been developed include:

1.       Thetsane and Tikoe, that are both in the Thetsane and Tikoe areas with major industrial (textile) development  at Thetsane.

2.       LEC Border 33/11 kV substation upgrade.

3.       Mafeteng and Quthing 33/11 substations.

Network Control

In 1987 a  supervisory control and data acquisition (SCADA) control system was installed at LEC headquarters, which improved supervision, and hence speedy detection and rectification of faults.

With the rapid pace of development of the control technology, the initial SCADA system is facing the following challenges:

1.       Outdated technology resulting in the un-availability of spare parts.

2.       Frequent breakdowns.

3.       Un-reliable network monitoring.

The upgrade of the SCADA system has since been implemented and the control covers more substations. This improves the restoration times when some term duration faults (for example, transients faults) occur on the network.

Communications Development

The initial communications for operating on the network, has been predominantly power line carrier (PLC-based) communication. The only limitation is the use of PLC telephones only when one is inside a substation where PLC exists.

The radio communication system has been implemented with the major drawback due to the terrain in Lesotho.

The latest development is the use of optic fibre means of communication. This is very reliable and with ample capacity. The other features include both data and voice transmission from the substations via the remote terminal units (RTU’s) to the control centre.

Back to top